Budget Search
County
North County Jail
Adopted Expenditures
By Program 2016-17 Adopted Change from 2015-16 Adopted
North Branch Main Jail Project
 
$32,389,202
100%
$9,979,713
44.5%
North Branch STAR Project
 
$0
0%
$1,662,000
100.0%
Total Department
 
$32,389,202
100%
$8,317,713
34.6%
Mission Statement

The Mission of the Northern Branch Jail project is to construct a modern and efficient AB900 Northern Branch Jail on time and within budget.

About the Department

The Northern Branch Jail Campus is located near the City of Santa Maria, California. The facility will be built on a fifty acre County-owned parcel located at the intersection of Black and Betteravia Roads.

In the Northern Branch Jail (AB900) Project, we are constructing a 134,000 square foot facility with capacity to hold 376 individuals. Estimated completion of the facility is November 2018 for the project.